Project Nexus

The UK Link system, operated by Xoserve for energy settlements, supply point administration and other functions for the GB gas market, is scheduled to be replaced.

Project Nexus aims to ensure that:

  • the replacement systems meet the current and anticipated requirements of market participants
  • market participants update their own IT systems to work with the new Xoserve systems.

In 2016, we took on a formal sponsorship role for Project Nexus (supported by PwC). Through the project, we want to ensure the IT system replacements currently underway are implemented to get the best possible outcome for consumers. This could include, for example, improvements to the settlement process by using the opportunities of more timely and accurate smart meter data.

In the publications and updates list below you can view outputs from the project as it progresses, alongside resources we produce to support industry participants.

Need help?

For questions about the project or the content of this page, please contact us.

Publications and updates

  • Published: 23rd Aug 2016
  • Agendas, minutes and presentations
  • 2 Associated documents
The items discussed at the sixth meeting of the Project Nexus Steering Group (PNSG) held on the 17 August 2016 are now available to view.

  • Published: 10th Aug 2016
  • Agendas, minutes and presentations
  • 2 Associated documents
The items discussed at the fifth meeting of the Project Nexus Steering Group (PNSG) held on the 1 August 2016 are now available to view.

  • Published: 29th Jul 2016
  • Agendas, minutes and presentations
  • 2 Associated documents
The items discussed at the fourth meeting of the Project Nexus Steering Group (PNSG) held on the 21 July 2016 are now available to view.

  • Published: 15th Jul 2016
  • Agendas, minutes and presentations
  • 1 Associated documents
This calendar overview will give clarity to the upcoming dates of Project Nexus meetings up to the end of 2016.

  • Published: 8th Jul 2016
  • Agendas, minutes and presentations
  • 2 Associated documents
See the items discussed at the third meeting of the Project Nexus Steering Group (PNSG) held on the 4 July 2016.

  • Published: 30th Jun 2016
  • Decisions
  • 1 Associated documents
We have decided to pursue option C - continue with programmed delay - as we believe this option provides for the earliest delivery of Project Nexus in line with our success factors.

  • Published: 15th Jun 2016
  • Agendas, minutes and presentations
  • 1 Associated documents
The items discussed at the fourth meeting of the Project Nexus Delivery Group (PNDG) held on the 14th June 2016 are now available to view.

  • Published: 15th Jun 2016
  • Agendas, minutes and presentations
  • 3 Associated documents
The second meeting of the Project Nexus Steering Group (PNSG) was held on 13 June 2016.

  • Published: 3rd Jun 2016
  • Closed: 22nd Jun 2016
  • Consultations and responses
  • 30 Associated documents
We are seeking stakeholders' views on PwC's recommended option for a successful implementation of Project Nexus.

  • Published: 2nd Jun 2016
  • Agendas, minutes and presentations
  • 2 Associated documents
The items discussed at the third meeting of the Project Nexus Delivery Group (PNDG) held on the 31st May 2016 are now available to view.