Monthly progress towards ECO3 phase 1 obligations

Chart

Javascript is required to render chart Monthly progress towards ECO3 phase 1 obligations.

Source: Ofgem analysis of supplier data.

Information correct as of: 01 May 2019

This chart shows energy companies’ cumulative monthly progress towards their phase 1 ECO3 obligations based on approved measures only.

Please note, the chart is based on the notification period (the month after installation of the measure).

Phase 1 of ECO3 ran from 03 December 2018 to 31 March 2019.

Phase 2 of ECO3 runs from 01 April 2019 to 31 March 2020.

Policy Areas:

  • Environmental programmes
  • ECO

Data Table

Monthly progress towards ECO3 phase 1 obligations
Notification Period (month after installation)HHCRO %HHCRO Rural %
Nov-180.94%1.03%
Dec-183.45%3.31%
Jan-195.50%5.65%
Feb-1911.64%12.18%
Mar-1920.14%20.72%
Date correct
01 May 2019