Monthly progress towards ECO3 phase 1 & 2 obligations

Chart

Javascript is required to render chart Monthly progress towards ECO3 phase 1 & 2 obligations.

Source: Ofgem analysis of supplier data.

Information correct as of: 05 August 2019

This chart shows energy companies’ cumulative monthly progress towards their phase 1 & 2 ECO3 obligations based on approved measures only.

Please note, the chart is based on the notification period (the month after installation of the measure).

Phase 1 of ECO3 ran from 03 December 2018 to 31 March 2019.

Phase 2 of ECO3 runs from 01 April 2019 to 31 March 2020.

Policy Areas:

  • Environmental programmes
  • ECO

Data Table

Monthly progress towards ECO3 phase 1 & 2 obligations
Notification Period (month after installation)HHCRO %HHCRO Rural %SWMR %
Nov-180.47%0.70%0.05%
Dec-182.15%2.95%0.99%
Jan-193.43%4.88%1.72%
Feb-195.43%7.34%3.79%
Mar-197.77%11.01%6.71%
Apr-1910.13%14.26%9.68%
May-1913.61%19.74%14.16%
Jun-1916.64%25.08%18.45%
Date correct
05 August 2019