Monthly progress towards ECO3 phase 1, 2 & 3 obligations

Chart

Javascript is required to render chart Monthly progress towards ECO3 phase 1, 2 & 3 obligations.

Source: Ofgem analysis of supplier data.

Information correct as of: 02 November 2020

This chart shows energy companies’ cumulative monthly progress towards their ECO3 phase 1, 2 & 3 obligations based on approved measures only.

Please note, the chart is based on the notification period (the month after installation of the measure).

Phase 1 of ECO3 ran from 03 December 2018 to 31 March 2019.

Phase 2 of ECO3 ran from 01 April 2019 to 31 March 2020.

Phase 3 of ECO3 runs from 01 April 2020 to 31 March 2021.

Policy Areas:

  • Environmental programmes
  • ECO

Data Table

Monthly progress towards ECO3 phase 1, 2 & 3 obligations
Notification Period (month after installation)HHCRO %HHCRO Rural %
Surplus Actions4.23%0.00%
Nov-184.63%0.59%
Dec-185.82%2.39%
Jan-196.70%3.83%
Feb-198.35%6.28%
Mar-1910.23%8.99%
Apr-1912.33%12.08%
May-1914.16%14.86%
Jun-1916.12%17.92%
Jul-1918.20%21.10%
Aug-1920.53%24.08%
Sep-1922.90%26.82%
Oct-1925.65%29.64%
Nov-1929.20%33.37%
Dec-1932.63%37.00%
Jan-2036.39%40.06%
Feb-2038.11%42.34%
Mar-2040.50%45.25%
Apr-2042.95%48.50%
May-2043.84%49.28%
Jun-2044.95%50.33%
Jul-2047.35%52.88%
Aug-2049.72%56.12%
Sep-2052.31%59.23%
Date correct
02 November 2020