Skip to contents

Charging 

 

There is a single electricity licence relating to the GB transmission system that covers both System Operator (SO) activities and Transmission Owner (TO) activities. There are currently three transmission licensees each of which is permitted to develop, operate and maintain a transmission system within a distinct transmission area (SPTL in south of Scotland, SHETL in north of Scotland and NGET in England & Wales).  The SO function, coordinating and directing flows onto and over the GB transmission system to balance electricity generation and demand, is carried out for the whole GB (to include offshore transmission networks) by NGET. Only one licensee is permitted to carry out SO activities.  The TO activity function involves the provision of transmission network services to the SO, enabling NGET to fulfil its SO licence obligations.

 

The provision of network services is linked to providing transmission capability at different locations and is facilitated by the TOs building, operating and maintaining their transmission assets. The allowed costs associated with providing this capability are set by Ofgem as part of the price control process and are recovered by NGET as SO, via contracts with users for connection to and use of the GB transmission system.

Users of the transmission system are subject to three types of transmission charges; Balancing Services Use of System (BSUoS) charges, connection charges and Transmission Network Use of System (TNUoS) charges, explained below.  Each type of charge is payable to NGET as SO. 

 

  • Connection charges - these are charges for the provision and maintenance of connection assets, which are assets solely required to connect a particular user (for example, a generator) to the main transmission system. The costs of these assets are recovered under the remit of the NGET's connection charging methodology. NGET defines "connection assets" as those assets solely required to connect an individual user to the GB transmission system, which are not and would not normally be used by any other connected party. The costs of these assets are recovered directly from the generator via connection charges.

 

  • The above definition used to derive connection charges excludes all assets which are shared or could be potentially shared by more than one user (transmission infrastructure assets). TNUoS charges recover the cost of the provision and maintenance of shared electricity transmission assets, or in other words, assets that cannot be solely attributed to a single user.  TNUoS charges are recovered from all users of the GB electricity transmission system. These charges vary by location, reflecting the costs that users impose on the transmission network to source (demand) or send (generators) their electricity.

 

  • BSUoS - these charges relate to the costs of the day-to-day operation of the transmission system and include charges for the recovery of constraints costs.

 

In terms of charging, the primary requirement of the Transmission Licence is that the various charging mechanisms should achieve the “Relevant Objectives” of facilitating competition; reflecting costs incurred; and taking account of developments in the transmission and connection businesses.


While the form of the methodologies must be approved by Ofgem, we do not set or approve the level of individual charges. It is the transmission companies’ responsibility to propose and consult on changes to the methodology.  Changes to the methodology are subject to a veto by Ofgem.


The transmission licence describes the process which must be followed as and when NGET wish to modify the charging methodologies in order that the relevant  objectives are better achieved.


NGET is required to consult on any proposed modifications with users and to submit its proposal to the Authority. Ultimately the Authority takes a decision on whether or not a modification may be made.



DateTitle (Click for more document information)
27/09/2011Approval of Scottish Power Transmission Limited's (SPTL) Statement of the Basis of Transmission Owner Charge
27/09/2011Approval of Scottish Hydro Electric Transmission Limited’s (SHETL) Statement of the Basis of Transmission Owner Charge
05/08/2011Scottish Power Transmission Limited (SPTL) re-consultation on modifications to Statements of the Basis for Transmission Owner Charges August 2011
- (Reference number: 101/11)
13/05/2011Consultation on modifications to Statements of the Basis for Transmission Owner Charges 2011/12
- (Reference number: 60/11)
26/01/2011Use of System Charging Methodology Modification Proposal GB ECM-27: “Balancing Services Use of System (BSUoS) – Removing End of Scheme Year Reconciliation Process”
18/10/2010Consultation on the discount for small transmission connected generators from 31 March 2011
- (Reference number: 130/10)
04/10/2010Decision letter in relation to Use of System Charging Methodology Proposal GB ECM-26 “Review of interconnector charging arrangements”
20/08/2010Approval of Scottish Power Transmission Limited's (SPTL) Statement of the Basis of Transmission Owner Charge
20/08/2010Approval of Scottish Hydro Electric Transmission Limited’s (SHETL) Statement of the Basis of Transmission Owner Charge
16/07/2010Decision letter in relation to Use of System Charging Methodology Proposal GB ECM-24 “Modification proposal to Transmission Network Use of System Charging Methdology to update charging arrangements associated with Offshore Transmission Networks"
04/05/2010Consultation on modifications to Statements of the Basis for Transmission Owner Charges 2010/11
- (Reference number: 55/10)
09/04/2010Decision in relation to the Use of System Charging Methodology Modification Proposal GB- ECM-21: 'Implementing a mid year tariff change'
08/03/2010Decision Letter of Modification to Special Condition D4 of the Electricity Transmission Licence of National Grid Electricity Transmission
01/03/2010Decision in relation to the Use of System Charging Methodology Modification Proposal GB ECM-18: “Locational BSUoS”
25/01/2010Notice of Consultation of Special Condition D4 (Pass Through Items)
- (Reference number: 9/10)
03/12/2009Intention to undertake an impact assessment on GB ECM-18: Locational BSUoS
03/12/2009GB ECM-18 Locational BSUoS Impact Assessment
- (Reference number: 149/09)
22/07/2009Modification of Transmission Standard Licence Condition (SLC) C5 and C6
- (Reference number: 83/09)
26/06/2009Approval of SPTL's Statement of the Basis of Transmission Owner Charges
26/06/2009Approval of SHETL's Statement of the Basis of Transmission Owner Charges
17/06/2009Open Letter on GB ECM-18 - Locational BSUoS (Balancing Services Use of System)
10/06/2009Conclusions in respect of the consultation to modify Standard Licence Condition C5 and C6 of the electricity transmission licence; and Notice under Section 11A of the Electricity Act 1989
- (Reference number: 64/09)
30/03/2009Proposal to modify Standard Licence Conditions C5 (“Use of system charging methodology”) and C6 (“Connection charging methodology”) of the electricity transmission licence.
- (Reference number: 32/09)
30/03/2009Decision in relation to the Use of System Charging Methodology Modification Proposal GBECM-08: “Introduction of charging arrangements associated with Offshore Transmission Networks”
25/03/2009Consultation on modifications to Statements of the Basis for Transmission Owner Charges 2009/10
- (Reference number: 25/09)
04/02/2009Introduction of Charging Arrangements Associated with Offshore Transmission Networks (GB ECM-08): Impact Assessment and Consultation
- (Reference number: 07/09)
09/01/2009Letter of intention to undertake an impact assessment on modification proposal GBECM-08
15/12/2008Authority decision on TNUoS charging methodology modification proposal GBECM-11
24/10/2008Charging Arrangements for Transmission Infrastructure Assets Local to Generation Connections (GBECM-11): Impact Assessment and Consultation
- (Reference number: 147/08)
25/09/2008Use of system charging methodology modification proposal GB ECM-11: Charging arrangements for generator local assets.
08/05/2008Impact of Larger Generating Units on GB Electricity Supply Frequency - Standards and Governance
- (Reference number: 61/08)
01/05/2008The Inter-TSO Compensation scheme 2008 and 2009
- (Reference number: 58/08)
04/04/2008Consultation on modifications to Statements of the Basis for Transmission Owner Charges
- (Reference number: 38/08)
28/03/2008SECTION 11 and 49A(1) of Electricity Act 1989 - Recovering the Costs of Temporary Physical Disconnection - CAP048
- (Reference number: 31/08)
26/02/2008CAP048: Recovering the Costs of Compensation for Temporary Physical Disconnection Section 11 Licence Consultation
- (Reference number: 18/08)
05/06/2007139/07 - Approval of statement pursuant to special condition J2 of SP Transmission licence
- (Reference number: 139/07)
05/06/2007140/07 - Approval of statement pursuant to special condition J2 of SHETL Transmission licence
- (Reference number: 140/07)
22/03/200748/07 - Recovering the cost of compensation for temporary physical disconnection (CAP048) - Open letter consultation and minded to statement
- (Reference number: 48/07)
06/02/200721/07 - Consultation on modifications to Statements of the Basis for Transmission
- (Reference number: 21/07)
22/01/200712/07 - Fulfilment of conditions attached to the Authority's approval of the GB transmission charging methodologies GB charging condition 2
- (Reference number: 12/07)
22/01/200713/07 - Fulfilment of conditions attached to the Authority's approval of the GB transmission charging methodologies GB charging condition 4
- (Reference number: 13/07)
15/12/2006Charging arrangements associated with GB SQSS design
- (Reference number: 215/06)
05/12/2006Use of system charging methodology modification proposal GB ECM-06: SQSS design variation based on customer requests
- (Reference number: 209/06)
15/11/2006Fulfilment of conditions attached to the Authority's approval of the GB transmission charging methodologies - GB charging condition 3
- (Reference number: 198/06)
14/11/2006Fulfilment of conditions attached to the Authority's approval of the GB transmission charging methodologies - GB charging condition 6
- (Reference number: 196/06)
11/10/2006Decision in relation to use of system charging methodology modification proposal GB ECM-05: Manifest data errors in the calculation of TNUoS
- (Reference number: 185/06)
26/07/2006Modification under Section 11A(3) of the standard conditions of the electricity transmission license
- (Reference number: 126/06)
26/06/2006Transmission Arrangements for Distributed Generation (TADG) working group: date of first meeting
- (Reference number: 106/06)
21/06/2006Transmission Arrangements for Distributed Generation (TADG) Working Group: Invitation and draft terms of reference
- (Reference number: 102/06)
31/05/2006Enduring transmission arrangements for distributed generation
- (Reference number: 92/06)
31/05/2006Proposal to modify Standard Licence Conditions C5 (Use of system charging methodology) and C6 (Connection charging methodology) of the electricity transmission licence and Standard Special Condition A5 (Obligations as regard charging methodology) of the g
- (Reference number: 93/06)
30/05/2006Approval of statement pursuant to special condition J2 (Basis of Transmission Owner Charges) of Scottish Power Transmission Ltd's (SP's) transmission license
- (Reference number: 90/06)
30/05/2006Approval of statement pursuant to special condition J2 (Basis of Transmission Owner Charges) of Scottish Hydro-Electric Transmission Ltd's (SHETL's) transmission license
- (Reference number: 91/06)
26/04/2006Fulfilment of conditions attached to the Authority's approval of the GB transmission use of system charging methodology
- (Reference number: 76/06)
13/04/2006Consultation on statements of basis of transmission owner charges
- (Reference number: 72/06)
24/02/2006Modification of Scottish Hydro-Electric Transmission Limited's electricity transmission licence pursuant to Section 11(1) of the Electricity Act 1989
24/02/2006Modification of SP Transmission Limited's electricity transmission licence pursuant to Section 11(1) of the Electricity Act 1989
27/01/2006Enduring Transmission Arrangements for Distributed Generators - Glasgow Seminar
27/01/2006Enduring Transmission Arrangements for Distributed Generators - London Seminar
16/12/2005Enduring transmission charging arrangements for distributed generation - invitation to an industry meeting
- (Reference number: 279/05)
16/12/2005Notice under section 11(2) of the Electricity Act 1989 - Transmission reliability incentive: SP Transmission Limited
- (Reference number: 283/05)
16/12/2005Notice under section 11(2) of the Electricity Act 1989 - Transmission reliability incentive: Scottish Hydro-Electric Transmission Limited
- (Reference number: 284/05)
28/11/2005Ofgem's final proposals for National Grid's transmission price control extension for 2006/7: Presentation to City Analysts
14/11/2005Fulfilment of conditions attached to the Authority's approval of the GB transmission use of system charging methodology
- (Reference number: 241/05)