Quality of Service Incentives 

 

The interruption incentive scheme has symmetric annual rewards and penalties depending on each DNO’s performance against their targets for the number of customers interrupted per 100 customers (CI) and the number of customer minutes lost (CML).

The proportion of revenue exposed under the scheme is 1.2 per cent for CI and 1.8 per cent for CML.

The amount of revenue exposure to quality of service has been informed by customer survey.

DNO interruption performance (CI and CML) are audited each year and an audit report is published detailing the accuracy of measurements and any adjustments if applied to their annual performance.

The telephony incentives are based on the results of ongoing customer surveys on DNOs' telephony performance.

 



DateTitle (Click for more document information)
28/03/2012BPI Report for ENWL One-off Exceptional Event Claim - Wigan - 27 October 2010
28/03/2012BPI Report for UKPN EPN One-off Exceptional Event Claim - Great Yarmouth -07 June 2010
28/03/2012BPI Report for NP NEDL One-off Exceptional Event Claim - Stella South - 26 June 2010
28/03/2012BPI Report for NP NEDL One-off Exceptional Event Claim - All of NEDL - November to December 2010
28/03/2012BPI Report for SSE Southern One-off Exceptional Event Claim - Portsmouth -26 June 2010
28/03/2012BPI Report for UKPN SPN One-off Exceptional Event Claim - Twickenham - 23 June 2010
28/03/2012BPI Report for WPD South West One-off Exceptional Event Claim - Lockleaze - 30 July 2010
28/03/2012BPI Report for NP YEDL One-off Exceptional Event Claim - All of YEDL - November to December 2010
03/02/2011Quality of Service Incentive Scheme - Audit of Interruptions Reporting 2009-10 Final Report
03/01/2011Quality of Service Incentive Scheme - Audit of Interruptions Reporting 2008-09 - Final Report
03/11/2010Notice of Section 11 modification of the Quality of Service Charge Restriction Condition 8
- (Reference number: 136/10)
07/06/2010Minded to position on the major supply interruption at Dartford Creek in July 2009
- (Reference number: 70/10)
12/01/20102008 / 2009 Electricity Distribution Quality of Service Data Tables
18/12/20092008 / 2009 Electricity Distribution Quality of Service Report
- (Reference number: 162/09)
19/12/20082007/08 Electricity Distribution Quality of Service Report
- (Reference number: 166/08)
20/11/2008QOS Incentive Scheme - Audit of Interruptions Reporting 2007.08 - Final Report
31/10/20072006-07 Electricity Distribution Quality of Service Report
- (Reference number: 268/07)
05/09/2007Quality of Service Incentive Scheme Audit Interruptions Reporting 2006.07 - final Report
04/01/20072005/06 Electricity Distribution Quality of Service Data
01/12/20062005/06 Electricity distribution quality of service report
- (Reference number: 204/06)
20/01/2006Information and Incentives Project: Audit of incident reporting 2004/05
15/12/20052004/05 Electricity Distribution Quality of Service Data
30/11/20052004/05 Electricity Distribution Quality of Service Report
- (Reference number: 258/05)
05/04/20052001/02 Electricity Distribution Quality of Service Data
05/04/20052003/04 Electricity Distribution Quality of Service Data
05/04/20052002/03 Electricity Distribution Quality of Service Data
24/03/2005Quality of Service Regulatory Instructions and Guidance Version 5
- (Reference number: 94/05)
16/02/2005Draft Quality of Service Regulatory Instructions and Guidance (rigs) version 5 - covering letter
- (Reference number: 49a/05)
01/02/2005Sixth Draft of Quality of Service Regulatory Instructions and Guidance version 5
- (Reference number: 49/05)
24/11/20042003/04 Electricity Distribution Quality of Service Report
- (Reference number: 260/04)
22/10/2004Information and incentives project: Audit of incident reporting 2003/4
- (Reference number: 244/04)
09/07/2004Directions under paragraphs 8 and 10 of Special condition G of the Distribution Licence - Central Networks East plc. Similar documents for other DNOs can be viewed by clicking on the +
05/07/20042002/03 Electricity Distribution Quality of Service Report
- (Reference number: 149/04)
29/03/2004Covering letter - Information and Incentives Project - Draft Regulatory Instructions and Guidance version 5
- (Reference number: 66a/04)
29/03/2004Information and Incentives Project - Draft Regulatory Instructions and Guidance version 5
- (Reference number: 66b/04)
25/03/2004Information and Incentives Project - Regulatory Instructions and Guidance version 4
- (Reference number: 63/04)
19/03/2004Information and Incentives Project: Audit of Incident Reporting 2002/03 Final Report
21/10/2003Information and Incentives Project - Regulatory instructions and guidance version 3
- (Reference number: 126/03)
21/10/2003Cover letter for Information and Incentives Project - Regulatory instructions and guidance version 3
- (Reference number: 126a/03)
31/07/2003Information and incentives programme: Proposed amendments to the Regulatory Instructions and Guidance for the speed of telephone response
- (Reference number: 76/03)
18/06/20032001/02 Electricity Distribution Quality of Supply Report
- (Reference number: 51/03)
04/03/2003Information and Incentives Project. Audit of Incident Reporting for 2001/02
06/12/2002Information and Incentives Project Report on Medium Term Network Performance Monitoring
01/10/2002Information and incentives programme - comparing quality of supply performance
27/03/2002Distribution Companies' Incident Reporting Systems - Interim Review Final Report
27/03/2002Information and Incentives Project (IIP) - Developing Audit Framework
31/12/2001Information and Incentives Project Final Proposals
- (Reference number: 78/01)
07/12/2001December 2000 Information and Incentives Project - Draft Regulatory Instructions and Guidance
09/11/2001Information and Incentives Project - Developing the Incentive Scheme Update
04/07/2001July 2001 Information and Incentives Project Summary of May 2001 IIP Workshop
03/05/2001Information and Incentives Project - Incentive Scheme Update
08/02/2001February 2001 Information and Incentives Project Regulatory Instructions and Guidance
08/02/2001Information and Incentives Project (IIP) - Final Version of Regulatory Instructions and Guidance (RIGS)
29/01/2001Guaranteed and overall standards of performance - Final proposals
- (Reference number: 09/01)
18/01/2001January 2001 Information and Incentives Project: Incentive Schemes - Initial Thoughts
07/12/2000December 2000 Information and Incentives Project Draft Regulatory Instructions and Guidance
29/09/2000Information and Incentives Project - Definition of Input and Output Measures
29/09/2000Information and Incentives Project Output Measures and Monitoring Delivery Between Reviews - Final Proposals
29/05/1999Quality of supply: attitudes of business and domestic electricity customers. Research study conducted for OFFER by MORI, January - March 1999
29/05/1999Supply interruptions following the Boxing Day storms
29/11/1998Report on distribution and transmission system performance 1997/98
29/11/1998Investigation of alledged breach by National Power of generation licence condition.